INTRODUCTION
Assembly
processing is one of the rarely used but extremely robust process used
in various industries. This process encompasses the functionalities of
receiving the order and planning all the requirements of the order by
passing the requirements to various other related modules. Once all the
components are received they are assembled and handed over to customer.
Based
on the business requirement, a sales order can lead to any of the
orders including production order, planned order, a network or a
process order. Based on this linkage configurations are to be done in
the respective modules along with configurations in sales and
distribution.
This
chapter explains about the creation of a network in project systems
while creating a sales order in SD. The functionality of assembly
request can also be linked with various other functionalities like
milestone billing in SD, milestone management in PS, Schedule and cost
management in PS etc. However this document concentrates only on the
configuration required for creating a network automatically when a sales
order is created. During the course of the document, some of the
obvious configurations are assumed to be known to the basic consultant
and hence not dealt in much detail.
PROCESS FLOW
The
process starts with the creation a sales order using a material code.
The material codes in this case are very limited and are specific to
every variation.
The
sales order item will trigger a requirement transfer. As a result the
requirement class triggers a network considering the requested delivery
date of the sales order as the finished date of the network. At the same
time, a project is created for the entire sales order and WBS element
will be created for each of the line item.
If
the network is enabled with milestones for activities, then milestone
billing can be automatically triggered in sales order if the item
category is also accordingly configured.
Now
we have a sales order, a project for it, various line items each item
having a WBS element and a network. Now it is possible to manage each of
these line items in PS using schedule and milestone management.
Accordingly when milestones are confirmed in PS, milestone billing can
be triggered in sales orders.
At
the end when all the items are delivered the project can be settled and
closed. This document doesn’t deal about deliveries for project as my
knowledge level in this area is minimal.
CONFIGURATION TRANSACTION CODES
Though
I have the system with me, I don’t want to put the screen shots because
of customer confidentiality. Hence I am trying to explain as much as
information through text. In case of any doubt the same can be discussed
in the comment on this content.
VOV8
VOV7
VOV6
Configuration Paths in Transfer of Requirements
CN91
CN08
CL24N
CN01
STEPS IN CONFIGURATION
The
first of the configuration is the sales order type. This is the basic
configuration in SD and hence I skip this configuration.
The
header configuration is followed by the item category configuration. If
milestone billing functionality is to be used, then the Billing plan
type in the item category should have a value indicating the Milestone
billing. A copy of billing plan type can be made by copying the billing
plan type 01. Similarly the billing relevance can be maintained as I for
billing based on billing plan and order related billing. Except this
all the other settings for item category is same for assembly processing
as for any other processes. Also it should be remembered that variant
configuration is a robust functionality used in assembly processing to
dynamically determine various project and sales parameters and hence the
item category should also consider the use of variant configuration if
needed.
Schedule line configuration is same as the normal schedule line configuration and hence I am not dealing much about it.
These
are followed by the configuration for transfer of requirements. This is
where the SD module is integrated with the PS module. It involves the
following steps to determine the strategy group or the strategy type. It
can be based on the normal rules for TOR. The strategy group can be
determined from any one of the following methods viz…the combination of
item category and MRP type,from material master and so on. Using this
configuration either the requirement class is determined using the
strategy group (if the strategy group is maintained in material master)
or using the requirement type (if the MRP type is maintained in material
master). The requirement class is the one which
dictates the integration between SD and PS and the desired requirement
class can be seen from the transaction code OVZG. The configuration at
the requirement class should have the following fields filled.
The availability button should be switched off as the material availability is not enabled in assembly processing.
The field Requirements transfer should be ticked on in the requirement class
The assembly type should be 2. This will ensure that a network is created automatically if the relevant configurations are done.
The field Order type should be filled with the network type which is to be created while creating sales order.
The field Capacity check can have the value as 1 or 2 based on requirement of capacity
The
fields related to costing and configuration can be left empty here as
they can also be handled in other places which will take precedence over
this configuration.
The field special stock can have the value as E to make sure that stock is reserved against the sales order.
The field Account Assignment Category should
be enabled with the value D. This will ensure that the project or its
subordinate levels can be used as account assignment objects. Based on
the configuration in PS either the network and activity number or the
WBS elements can be used as the account assignment objects.
The field Consumption should be configured with the value P to ensure project based consumption.
These
fields are the mandatory fields to be updated. The remaining fields are
optional and can be configured based on need. The fields related to
costing, settlement, and valuations are best left empty here and
configured in the respective modules.
Once these configurations are done in SD the process will work as follows.
When
a sales order item is put, based on its item category, schedule line
category configuration, the transfer of requirements is triggered and
the correct requirement class is determined. Using the requirement class
the system will try to create a network. However to create a network
system will need another set of data from PS module. The set of data
needed after doing the basic set of PS configuration are explained here.
At first a standard project should
be created in PS using the transaction code CJ91. In order to do this
the project definition, the project profile etc are needed and the PS
consultant will be in the best position to configure the project profile
for this activity.
A standard project should also include a standard WBS element with
all the necessary set up like planning element, account assignment
element, billing element and other organisational elements. The creation
of standard project and standard WBS element should follow the coding
mask and the coding mask should take care of the number of characters
for the sales order. Because any operative project or the WBS element
will have the sales order number in the project as a standard
functionality in assembly processing. For example if the coding mask is
enabled as A/xxxxxxxxxx/ _____ then the characters xxxxxxxxx represent
the sales order and the code with 10 characters will be used to fill up
the sales order number while creating the project.
This is followed by the creation of standard network in CN01. The network can have the standard WBS element at the header and item level for all the activities if necessary.
Also
in parallel the material master should also be set up by the MM
consultant to be used in Sales order. The material master should have
all the four MRP views and the MRP type should be kept as ND or the
relevant MRP type to trigger the correct requirement type and hence the
correct requirement class. If the MRP type is maintained as ND, then the
strategy group should be maintained as the correct group which directs
to the desired requirement class for the customer requirement.
Once these set up are completed, the final set up will be in the transaction code CN08 where
the material code will be linked to a standard network. This data
should have the correct network order type as maintained in the
requirement class. Also the standard WBS element maintained in this
transaction code should be the one which is used in the network.
Generally in standard network we use only one standard network. If
multiple standard WBS elements are used in standard network activities,
then in CN08, this field can be maintained with empty values. The
values MRP controller and the network profile are mandatory and should
be maintained by the PS consultant.
If
this is done in PS the transfer of requirements while trying to search
for the network will have the necessary set up in CN08 and it will
create an operative network.
It
is also possible to have variant configuration enabled in assembly
processing. Using this for example based on the complexity of the
configuration and the activities required, different standard networks
can be mapped to the same material using CL24N.