FI
the Financials module can be thought as the 'core' of any integrated
SAP System because everything that has a monetary impact in the other
modules (where the 'real' business operates) flows through to FI -
usually in real time and automatically through the configuration.
Usually there is pressure to get going with the prototyping asap. When
the other modules start prototyping their transactions, the SAP system
is going to want to post the financial impact to FI. Thus the sooner
that you (the FI/CO configurer) can get some core FI/CO configuration
going the better for all.
Remember
all SAP configuration is essentially maintaining entries in a variety
of linked tables. Usually you need to maintain each little link or
entry step by step. Some new SAP configurers expect the transactions to
be as 'complete' as a user transaction - configuration is different. In
R/2 days we had to just know what tables to maintain - count yourself
lucky that you have the IMG now!
Following
are some guidelines (in increasing levels of functionality) to the FI
minimum configuration or master data setup for a new company code.
Follow the logical path in the IMG.
- Minimum configuration to post a journal in FI
- Minimum configuration to see expenses by cost center / post through to the CO Module
- Minimum configuration to post to sub ledgers (AR, AP)
- Minimum configuration to post from logistics modules to FI/CO (similar concept for other modules)
1. Minimum configuration to post a journal in FI:
(The
assumption is that you do not want to copy either the standard SAP
company or an existing company code because it will copy across too much
that is not similar or not required and therefore too much cleanup will
be required).
Initial Business Decisions Required:
Item to be decided
|
Comment
|
Code of company code (4 Digit Alphanumeric)
|
You could setup new one later, copying the configuration
|
Code of Chart of Accounts
|
Not very visible, but the maintainers of the chart may want to decide this name
|
Length
of the GL A/c number and the account number range guidelines, possibly
also the numbers of some key accounts required for automatic postings
(see below)
|
SAP
allows 10 digits, however 5-7 appears to be the normal range.
Typically the number of accounts should be in the low hundreds. Decide
on the ranges of numbers for each type of account as much as you can so
that the team can start getting used to them. EG: standard SAP usually
has 4xxxxx as expense accounts, 11xxxx as Bank Related accounts etc.
|
Configuration steps:
Step
|
Comment
|
Define the company code
|
IMG
|
Define the name for a chart of accounts
|
IMG
|
Maintain the global parameters
|
IMG - Use standard SAP variants for the parameters to start with & update later
|
Define the default amount tolerances
|
IMG - Define for a blank group - so any new test user can post during prototyping
|
Define document number ranges
|
IMG - Copy from the standard ranges
|
Create some of the minimum accounts needed to start off with.
|
GL Master data:
Suggest
you create with reference from the standard chart and company code and
use those specifications (account groups, fields status groups etc) for
now, so that these accounts will be reasonably appropriately setup. A/R and A/P control a/cs, a petty cash or suspense a/c to hold sundry offset postings while debugging, a revenue account, some expense accounts. This list will expand as you go - see the section on account determination. |
Now
you should at least be able to post a GL journal. To test I suggest you
use balance sheet accounts only, since you will not have setup the cost
elements for the expense accounts. All projects would at least be using
the Cost center and Cost Element functionality of CO as a minimum. So -
on to the next step.
2. Minimum configuration to see expenses by cost center / post through to the CO Module
Initial Business Decisions Required:
Item to be decided
|
Comment
|
Structure of standard cost center hierarchy
|
The
structure should follow the organizations intended responsibility
reporting hierarchy (the budgetary responsibility). Allow the
appropriate number of levels.
|
Hierarchy node name coding
|
The
coding of the nodes is quite important because they can be used to
report on the levels in the standard reports, and so will be very
visible to the users
|
Cost Center Naming Standards
|
Useful to begin following the intended standards ASAP so that test data looks as real as possible.
|
Configuration steps:
Step
|
Comment
|
Define the controlling area
|
IMG, not very visible to users, if you are only going to have one, you could default it later
|
Assign the company code to the controlling area
|
IMG
|
Create the beginnings of the standard cost center hierarchy
|
CO - Cost Center Master data
|
Create a representative set of cost centers, assigning them to the appropriate node in the cost center hierarchy
|
CO - Cost Center Master data
|
Create all the expense accounts as primary cost elements
|
Either in the IMG - for all GL accounts in a specific range, or individually in the CO - Cost Center Master data
|
Now
you should be able to post a GL document (journal) to an expense
account and code it to the cost center. The posting should then be
viewable via Cost Center reporting and GL Account line Item Display.
3. Minimum configuration to post to sub ledgers (AR, AP)
Initial Business Decisions Required:
Item to be decided
|
Comment
|
GL Account Number of Control accounts
|
see account number range comments above
|
Configuration steps:
Step
|
Comment
|
Create the AP and AR Control accounts in the GL
|
see account creation comments above
|
Create a couple of customer and vendor accounts
|
If
using SD and MM too, inform the SD and MM analysts so that they can
complete the account creation on the SD/MM side for the customer and
vendor respectively.
|
Now you should be able to post a FI-AR customer invoice and an FI-AP vendor invoice.
4. Minimum configuration to post from logistics modules to FI/CO (similar concept for other modules)
So
far it was relatively easy going, now it starts getting a little more
difficult. Following are the very broad steps - for more detail see the
sections on Organization structure and Integration.
Initial Business Decisions Required:
Item to be decided
|
Comment
|
SD and MM organization structure and relationship to the FI/CO elements
|
Not
a trivial decision, and may require rework, so at this stage, decide on
a simple best guess with the SD/MM team to get you going
|
Configuration steps:
Step
|
Comment
|
Assign the SD and MM organization elements to the FI/CO elements
|
IMG;
to get prototyping going you need at least 1 set of working
relationships that the whole team can work with (EG: 1 Sales Area, 1
Purchasing Organization, 1 Plant etc)
|
Maintain the basic automatic account determination for each module
|
IMG;
For example : Revenue Account Determination for SD. As the modules
test or prototype expanded functionality, the SAP will look for the
accounts to which it should post. You could maintain on an as needed
basis. The SAP documentation and configuration does not always explain
clearly which piece of account determination is used for which type of
functionality, so it is sometimes difficult to be pro-active. being
reactive has the benefit that hopefully each side (e.g.: MM and FI) can
develop an understanding of what the business transaction is and
therefore where it should be posting. Otherwise the MM person may not
even be aware that he has generated a certain type of posting ! (You'd
be amazed at some of the lack of ownership from a logistics consultant
for the financial postings that they generate).
|