Project Definition
Project
Definition is general description of the project that you want to
manage. It is a framework laid down for all the objects created within a
project. It contains organizational data that is binding for the entire
project.
Work Breakdown Structure (WBS)
WBS is a hierarchical model
of the tasks to be performed in the project. It provides overview of
the project and forms basis for the project organization and
coordination.It shows work, time and money spent on the project. You can
use it to plan dates & costs and allocate budget. The Work
Breakdown Structure can be displayed according to:
· Phase
· Function
· Object
Individual tasks required to carry out the project is called WBS elements. Network
The
network describes project processing. Thus the Network contains
instructions on how to carry out activities in a specific way, in a
specific order and in a specific time period.Main elements of network
are activities and relationships. It forms the basis for planning,
analyzing and monitoring time schedules, costs, & resources.
Activities
Activities
are used to plan project staffing, capacity, material, PRTs, and
service requirements. When activities are assigned to WBS elements,
detailed view of costs, dates, and capacities at WBS element could be
obtained. It’s a task in a network which has a defined start and finish.
An activity can be broken down into activity elements.Three categories
of activities in the Project System:·
· Internal Activities
· External Activities
· General Cost Activities
Activity element
Activity
element is an activity which is subordinate to another activity.
Activity elements contain the same information as activities.Three
categories of activity elements in the Project System:
· Work elements
· External Elements
· General Cost Elements
Activity Type
It’s
a physical measure of activity output of a cost center .e.g. hours,
number of units produced, machine times, production times.
Milestones
Milestones
are the events in the project to which particular importance is
attached Or which trigger predefined functions. In general they indicate
transition between different departments or phases. Milestones are
assigned to activities and WBS elements:In PS milestones are used to:
· Trigger predefined functions in network activities.
· Carry out earned value analysis.
· Determine dates in billing plan for sales orders.
Relationships
You
use relationships to depict chronological and technical dependencies
between activities. The relationship determines the nature of the link
between the individual activities. :
· FS Relationship : An activity does not start until the preceding activity is completed.
· SS Relationship : An activity can not start unless another activity has started.
· FF Relationship : An activity can not be completed until another activity has been completed.
· SF Relationship : An activity can not be completed until another succeeding activity has stared.
Confirmations
It
is a part of network control. It documents the state of processing for
the network activities and activity elements. There are two types of
confirmations Partial & Final.Confirmations are used to record:
· The work center where the activity was carried out.
· The person who carried out this activity.
· The yield and scrap produced in an activity.
· The actual values for the duration and dates.
Settlement
As
a rule, projects are used to collect and monitor costs, but are not
usually the final cost object. For this reason the costs in atypical
project will be settled at the end of the period.To this end, you store
settlement rules in the activity / WBS element requiring settlement.
They contain information on settlement receivers, cost apportionment and
control data. Settlement receivers could be cost centers, G/L accounts.
Etc.
Budget
The
budget is the approved cost structure for an action or project in a
particular period.Budgeting differs from cost plan in that it is
binding. In the approval phase you prescribe your project funds in the
form of budget. It is possible to allocate overall and annual budget in
parallel.
Work Centers
Work
center represents the resources responsible for executing an activity.
In a work center, you can enter the available capacity and an operating
time. You can arrange the work centers in a hierarchy for capacity
evaluation purposes. Internal activities are assigned to work centers
(resources) to be completed.A work center is a physical unit within a
company where an activity is performed.