Network and activity related transaction codes:

CN01    Create Standard Network
CN02    Change Standard Network
CN03    Display Standard Network
CN04    Edit PS Text Catalog
CN05    Display PS Text Catalog
CN06    MPX Download: Standard Network
CN07    MPX Upload: Standard Network
CN08    Allocate material -> stand. network
CN09    Allocate material -> stand. network
CN11    Create standard milestone
CN12    Change standard milestone
CN13    Display standard milestone
CN19    Display Activity (From DMS)
CN20    Dsply network/act.bsc data init.scrn
CN21    Create Network
CN22    Change Network
CN23    Display Network
CN24    Overall Network Scheduling
CN24N   Overall Network Scheduling
CN25    Confirm Completions in Network
CN26    Display Mat.Comp/Init: Ntwk,Acty,Itm
CN26N   Display Mat. Components (From DMS)
CN27    Collective confirm.
CN28    Display Network Confirmations
CN29    Cancel Network Confirmation
CN2X    Confirm Completions in Network
CN30    Processing PDC error records
CN33    PDM-PS interface
CN34    Maintain release table TCNRL
CN35    Control stock / account assignment
CN36    BOM Transfer Profile
CN37    BOM Allocation Field Selection
CN38    Maintain Flexible Reference Point
CN40    Project Overview
CN41    Structure Overview
CN42    Overview: Project Definitions
CN42N   Overview: Project Definitions
CN43    Overview: WBS Elements
CN43N   Overview: WBS Elements
CN44    Overview: Planned Orders
CN44N   Overview: Planned Orders
CN45    Overview: Orders
CN45N   Overview: Orders
CN46    Overview: Networks
CN46N   Overview: Networks
CN47    Overview: Activities/Elements
CN47N   Overview: Activities/Elements
CN48    Overview: Confirmations
CN48N   Overview: Confirmations
CN49    Overview: Relationships
CN49N   Overview: Relationships
CN50    Overview: Capacity Requirements
CN50N   Overview: Capacity Requirements
CN51    Overview: PRTs
CN51N   Overview: PRTs
CN52    Overview: Components
CN52N   Overview: Components
CN53    Overview: Milestones
CN53N   Overview: Milestones
CN54N   Overview: Sales Document
CN55N   Overview: Sales and Dist. Doc. Items
CN60    Change Documents for Projects/Netw.
CN61    Standard network
CN65    Change documents order /network
CN70    Overview: Batch variants
CN71    Create versions
CN72    Create Project Version
CN80    Archiving project structures
CN81    PS: Archiving project - preliminary
CN82    PS: Archiving project structures
CN83    PS: Archiving project - Info System
CN84    PS: Archiving project - admin.
CN85    PS: Delete operative structures
CN98    Delete Standard Networks
CN99    Archiving Standard Networks
CNB1    Purchase requisitions for project
CNB2    Purchase orders for project
CNC4    Consistency checks for WBS
CNC5    Consistency checks sales order/proj.
CNE1    Project Progress (Individual Proc.)
CNE2    Project Progress (Collective Proc.)
CNE5    Progress Analysis
CNG1    Netw./Hier.: Maintain frame types
CNG2    Netw./Hier.: Maintain form def.
CNG3    Netw./hier.: maintain color definit.
CNG4    Netw./Hier.: Maintain graph. profile
CNG5    Netw./Hier: Maintain options profile
CNG6    Netw./hier.: Maintain node type
CNG7    Netw./Hier.: Maintain link types
CNG8    Netw./Hier.: Maintain field def.
CNG9    Graph. Cust. Netw./Hierarchy Graph.
CNL1    Create delivery information
CNL2    Change delivery information
CNL3    Display delivery information
CNMASS  Mass Changes in Project System
CNMASSPROT      Display log f. mass changes PS
CNMM    Project-Oriented Procurement
CNMT    Milestone Trend Analysis
CNN0    Number Range for Library Network
CNN1    Number range maint.: ROUTING_0
CNPAR   Partner Overview
CNPRG   Network Progress
CNR1    Create Work Center
CNR2    Change Work Center
CNR3    Display Work Center
CNS0    Create deleivry from project
CNS40   Project Overview
CNS41   Structure Overview
CNS42   Overview: Project Definitions
CNS43   Overview: WBS Elements
CNS44   Overview: Planned Orders
CNS45   Overview: Orders
CNS46   Overview: Networks
CNS47   Overview: Activities/Elements
CNS48   Overview: Confirmations
CNS49   Overview: Relationships
CNS50   Overview: Capacity Requirements
CNS51   Overview: PRTs
CNS52   Overview: Components
CNS53   Overview: Milestones
CNS54   Overview: Sales Document
CNS55   Overview: Sales and Dist. Doc. Items
CNS60   Change Documents for Projects/Netw.
CNS71   Create versions
CNS83   PS: Archiving project - Info System
CNSE5   Progress Analysis
CNVL    Variable Overviews
CNW1    WWW: Confirmation
CNW4    Project Documents